    Dear TRIUMF Users, Experimenters, Operators and Staff,
    <br>
    <br>
    This is to update you on the current situation with ongoing repair
    in Beam Line 1A (BL1A), and the impact on <a
href="https://mis.triumf.ca/schedule/view?schedule=119b&amp;revision=ACTIVE">Schedule
      119b</a>.
    <br>
    <br>
    As you know, we had foreseen an extended shutdown period for BL1A,
    over the rest of the cyclotron-based program, due to necessary
    repairs. We had planned to start beam production August 10, 2011.
    However, after uncovering shielding and doing more detailed analysis
    it was discovered that more substantial repairs are needed than
    originally anticipated. The scope of the repair has been assessed in
    detail and an in-depth plan has been put together. With this plan,
    which requires extended shift work from the service groups, and help
    from all TRIUMF divisions, we are planning and are confident to
    start beam production for BL1A users August 19, 2011, with the
    possibility to provide discretionary beam potentially earlier
    (around August 16, 2011).
    <br>
    <br>
    This is reflected in the online Schedule 119b. We currently assume
    operation with a T2 target in place, however we are considering
    operation without target (and hence no beam production for M9), as
    this would allow operation at much reduced activation of the
    temporary shielding and much reduced shielding movement. It would
    also provide possible access for the installation of the new muon
    channels. The potential benefit of this T2 target-less operation is
    also a much reduced scope of the upcoming schedule 120 shutdown and
    earlier beam production for Schedule 121. Schedule 121 will at this
    point be able to operate with the new muon channels M9 (a/b) and
    M20. We are assessing the situation and will inform you if we are
    making changes, hence opt for target-less operation.
    <br>
    <br>
    For Schedule 120, which will run for the Meson Hall-operation from
    September 23 to December 23 and for ISAC-operation from October 6 to
    December 23, a call for beam requests will go out in the next 2
    weeks.
    <br>
    <br>
    Thank you for your patience.
    <br>
    <br>
    Sincerely,
    <br>
    Jens Dilling
    <br>
    <pre class="moz-signature" cols="72">-- 
Miss Nicole (Niki) Martin
Administrative Assistant
Science Division

TRIUMF